Please ensure Javascript is enabled for purposes of website accessibility

Almost done: Long-running Longboat Key projects near completion

Underground utilities and a sea level rise study are among projects near completion at the end of the year.


  • By
  • | 5:00 a.m. November 30, 2022
Neighborhoods on the north end are more prone to flooding during high tide.
Neighborhoods on the north end are more prone to flooding during high tide.
  • Longboat Key
  • News
  • Share

Not unlike other jurisdictions across the nation, the town of Longboat Key has a laundry list of projects to complete. 

Of the 18 active projects on the town's Public Works Department's to-do list, some are nearly wrapped up, some are under way but with some work to be done and some are still in the planning stages. 

This week, the Longboat Observer will run through all of them and update their status as 2022 begins coming to an end. Follow along on pages 5 and 7 for updates on the other stages of project work. 


Underground utility project

The town’s underground cable project is nearing completion with nearly all stages of all phases finished. 

In the underground electrical design-build portion of the project, all work is done in phase 1. All underground infrastructure work is also complete in phases 2 and 3. 

For phase 2, switching orders were submitted in August, but were delayed to allow for focus on restoration efforts after Hurricane Ian. On Oct. 27, the town received word that the orders have been re-engaged. All that remains in the phase is making final connections to all phase 2 meters and incrementally energizing them.

Town underground infrastructure work is on track to be completed by Dec. 31.
File photo

"(The storms) both impacted our project because when a storm of that magnitude approaches Florida, FPL redirects all of their resources toward storm preparation and then post-storm recovery," Public Works Director Isaac Brownman said. "All the work we were doing to get ready to start switch orders in phase two essentially got put on hold so FPL could divert their resources towards storm efforts."

In phase 3, Florida Power and Light has approved redline drawings and re-engaged the switch order process. Crews have installed service runs to the meter, which will expedite the meter conversion process. Final steps in the phase are the same as those in phase 2. 

In phase 4, all conduit boring operations are complete. Crews have installed all but five switch chambers on Gulf of Mexico Drive. The remaining chambers are on a manufacturing delay. Crews are on standby and ready to set them as they become available. The town is targeting December for the work. Redlines are being prepared for FPL, so they can be approved and allow for the switch order process to begin. 

Nearly all neighborhood street lights are installed in all phases. The GMD highway lights were scheduled for installation at the end of November. 

According to the updated master schedule, all underground electrical infrastructure work remains on track to be complete on or before Dec. 31 including the give chambers for phase 4 currently on backorder. Installation of backordered street lights for GMD is also anticipated by Dec. 31. 

Brownman expressed hope that energizing of the whole of the new underground system will be complete by spring 2023. Remaining work, including removing poles and wires, is the responsibility of the FPL. Once FPL work is complete, the project will be fully finished, which Brownman expressed should be around mid-summer 2023. 

Next steps include: 

  • Begin switching orders, meter conversions and energizing in phases 2 and 3. 
  • Obtain five vault chambers, set remaining equipment and pull related wire in phase 4. 
  • Begin switching orders, meter conversions for phase 4. 
  • Finish all easements 
  • Complete all practical street light installations. 
  • Determine costs and ROI merits of town fiber solution. Proceed accordingly. 
  • Continue working with telecommunications providers to enhance coverage improvements on the island as well as planning of future smart city, cellular or fiber project elements. 
  • FPL pole removal and final streetlight installations


Sea level rise study 

All that is left to complete in the town’s sea level rise study is the last portion of phase 4, the implementation plan. Phase 1, 2 and 3 are all complete. Phase 1 was categorized as the initial assessment. Phase 2 included data collection and analysis. Phase 3 was adaptation recommendations. 

APTIM Environmental and Infrastructure conducted the study for the town as it works toward implementing changes to deal with expected environmental changes. 

The town has received about $131,289 to support the project.

Among the initial impacts discovered in phase one, APTIM found the town’s Public Works Complex, Recreation Center and Fire Station 92 are subject to nuisance flooding whereas the Mid-Key Water plant is subject to more serious disturbance flooding. APTIM’s report found the police station, Town Hall and South Key Water Plant have unlikely short-term risks.

The report found the Mobil gas station, the town’s only filling station, is prone to disturbance flooding. However, other commercial businesses such as the Bank of America, Suntrust Bank complex, Cannons Marina and Harborside Marina are subject to nuisance flooding.

The post office, Publix, Mediterranean Plaza, First Bank and CVS Pharmacy have unlikely short-term risk.

As mentioned above, nuisance flooding is flooding that often happens during high tide. Disturbance flooding is defined as flooding of more than 1 foot of water on the road where it is dangerous to drive; some parts of the road might close. Impact flooding is flooding from hurricanes or major storm surges.

Staff will provide an update to the commission at its Dec. 12 workshop. The town already dedicated American Rescue Plan Act funds, about $1.8 million, to help offset costs of recommended actions. A full scope of costs is still in the works with staff planning to pursue relevant grant funding for remaining costs. 


Drainage assessments

Under the same umbrella as the sea level rise study, the town conducted drainage assessments of the Sleepy Lagoon and Buttonwood Harbour neighborhoods, which historically experience flooding issues during heavy rain and high tide. 

"One of the primary enhancements recommended is raising the roads," Brownman said. "It's just the reality of the town. We are a barrier island and portions of the island were built extremely low years ago...there's not a lot that can be done with the existing infrastructure without raising the road."

Data collection, area elevation and topographic surveys have been completed. The town commission will be updated at its Dec. 12 workshop before next steps are finalized. Kimley-Horn, a planning and design consulting firm, conducted the neighborhood-specific studies. 


 

Latest News