County commissioners voted to add up to $103,750 to the contract to repair Blackburn Pont Bridge in Osprey.
The original schedule for the repairs to the 83-year-old bridge called for the work to begin earlier this month, but residents on Casey Key and along Blackburn Point Road asked the county to delay the month-long job until the end of May.
The county rescheduled the commencement date to May 26. With hurricane season beginning June 1, the new schedule puts most of the work during hurricane season.
So, the county’s public works department asked commissioners to sign off on an amendment to the work contract to account for the added risk.
The amendment includes $5,000 for a contractor to prepare for a possible storm and an additional $49,375 to secure the bridge during each of up to two storms that might threaten the area.
The revised total cost of the project is now $4.9 million.
The historic swing bridge will have nearly all of its mechanisms repaired or replaced during the work.
Currently 0 Responses
- May
26 Celtic Curse: An Yvonne Suarez Travel Mystery
1:00 pm - May
26 Memorial Day Concert/Service
4:00 pm - 5:00 pm - May
26 USFSM Open House
6:00 pm - 7:30 pm - May
27 Gentle Yoga and Meditation with Lynn Burgess
10:00 am - 11:00 am
-
Jolly good fellow
05/23/13
Just as Observer advertising representative Bob Lewis loves to garden, he also cultivates relationships with all of his co-workers and clients. -
Going for the gold
05/23/13
Sisters Francesca and Elizabeth Martel returned victorious Monday, May 20, after a weekend at the Special Olympics of Florida State Summer Games, in Orlando. -
Culinary roots
05/16/13
Trevor Kunk is the chef de cuisine at Blue Hill in New York City’s Greenwich Village, which the James Beard Foundation just named "most outstanding restaurant."