Construction of an 8-foot bicycle path is moving quickly, according to Darren Alfonso, the repavement project’s public information officer for the Florida Department of Transportation.
Work on the path began Monday, June 1, near the Longboat Key Club and Resort Islandside and continued north on Gulf of Mexico Drive. As of Thursday, June 4, construction work was continuing near The Colony Beach & Tennis Resort, 1620 Gulf of Mexico Drive.
AJAX contractors also began paving operations Sunday, May 31, at Bird Key Drive, continuing west to North Adams Drive. Lane closures in that area continue between 6:30 p.m. and 6:30 a.m. each day. Repavement of St. Armands Circle will begin in approximately a week-and-a-half, Alfonso said.
Major paving operations on Gulf of Mexico Drive from the Sarasota County line to the Longboat Pass Bridge were completed May 13. Re-striping of the roadway is scheduled for June 15.
For more information, contact Alfonso at 813-767-9532.
Contact Robin Hartill at rhartill@yourobserver.com.
Currently 0 Responses
- Sep
10 The Argus Foundation Fall Golf Tournament
11:00 am - Sep
14 Tony Blair & Katie Couric "Live" at the 92nd Street Y
8:00 pm - Sep
24 Introduction to the Ocean: 101 for Adults
9:00 am - 11:00 am - Sep
26 4th Annual "Shipreck" Poker Run
10:00 am - 6:00 pm
-
Parking lot may be closed, but we're open for business
09/01/10
The parking lot is getting new landscaping and is currently closed. -
Annual Community Harvest fundraiser begins at The Columbia
09/01/10
This year, the St. Armands Circle Columbia restaurant location has partnered with 16 charities from which customers can choose. -
Rusty Chinnis snaps up four outdoor writing awards
09/01/10