Please ensure Javascript is enabled for purposes of website accessibility

Fort Hamer Bridge opening delayed

A run across it will continue as planned.


  • By
  • | 9:34 a.m. August 15, 2017
The Fort Hamer Bridge is almost completed, but punch-list items must be addressed to make it safe for vehicular traffic. Heavy summer rains are causing a delay for its opening. Courtesy photo.
The Fort Hamer Bridge is almost completed, but punch-list items must be addressed to make it safe for vehicular traffic. Heavy summer rains are causing a delay for its opening. Courtesy photo.
  • East County
  • News
  • Share

A celebratory run across the Fort Hamer Bridge will still go on as planned Aug. 26, but the bridge itself will not actually open to traffic until Sept. 23.

Trudy Gerena, spokesperson for the project on behalf of Manatee County, said summer rains caused the delay.

“We had over 38 inches from June to mid July and Tropical Storm emily came through. It slowed down production,” she said.

Contractor Johnson Brothers Corp. still will need to install guardrails and handrails on a portion of the bridge, give texture to the decks and stripe the roadway, among other final tasks.

 

Latest News